In JAMA, there currently isn't a way to revert back to a baseline set of requirements if new requirements have already been added.

Example:

  1. Version 1 requirements are created and released in SAP
  2. Version 2 requirements are in progress - with addition of new requirements and updates to existing requirements
  3. Unexpected hot fix version for Version 1 after starting Version 2: Version 1.1 requirements are in progress - with addition of new requirements to Version 1 and none of the Version 2 requirements

JAMA's baseline allows reverting back any modified requirements to the original version. However, any new requirements added will also be a part of that baseline. So, if we have to create Version 1.1, it will include Version 1 and Version 2 requirements. Is there any way we can support branching in JAMA from a specific baseline so that we can include only requirements from a specific set instead of a hybrid of two versions

Comments

  • Alex E
    edited November 2018
    Can you create a new project with synchronized copies of the requirements to achieve this?