Ability to support branching from previously released set of requirement in JAMA

  • 1.  Ability to support branching from previously released set of requirement in JAMA

    Posted 10-29-2018 15:49
    Hi
    In JAMA, there currently isn't a way to revert back to a baseline set of requirements if new requirements have already been added.

    Example:

    1. Version 1 requirements are created and released in SAP
    2. Version 2 requirements are in progress - with addition of new requirements and updates to existing requirements
    3. Unexpected hot fix version for Version 1 after starting Version 2: Version 1.1 requirements are in progress - with addition of new requirements to Version 1 and none of the Version 2 requirements

    JAMA's baseline allows reverting back any modified requirements to the original version. However, any new requirements added will also be a part of that baseline. So, if we have to create Version 1.1, it will include Version 1 and Version 2 requirements. Is there any way we can support branching in JAMA from a specific baseline so that we can include only requirements from a specific set instead of a hybrid of two versions



    ------------------------------
    Kamlesh Singh
    ------------------------------


  • 2.  RE: Ability to support branching from previously released set of requirement in JAMA

    Posted 11-05-2018 18:49
    Can you create a new project with synchronized copies of the requirements to achieve this?

    ------------------------------