Create Test Plan/ Test Runs from JAMA test case baseline

[Deleted User]
[Deleted User] Member Posts: 2
Hi,

Sometime ago I created baseline for my test cases in JAMA. After the baseline was created, we started updating the test cases for new version of the product. However, I still have to execute tests from baseline for previous version of the product. Is it any solution to create test plan based on the baseline which i created ( in the test plan/test cycle I would like to have test run corresponding with version of the test cases from baseline).

Any GUI option or REST API to support creating test run based on the specific version of the test case?

Thanks in advance
Bartek

Comments

  • Decoteau Wilkerson
    Decoteau Wilkerson Jama Staff, Data Exchange, Moderator, Automotive Solution, Medical Devices & Life Sciences Solution, Robotics Solution, Airborne Systems, Jama Connect Interchange™ (JCI), Jama Validation Kit (JVK) + Functional Safety Kit (FSK) Posts: 47
    edited April 2021
    Hi Bartek, 

    Thanks for reaching out! There is no way to create a Test Plan/Cycle on a Baseline. 

    You could visit our Ideation module and submit this as an idea. This is a valuable space where we solicit and gather product feedback. You can go here, and use the search functionality to see if your idea is already in there. If it is, then you can vote and comment on the card. If there isn't, please post a new idea card. 

    Let us know if you have any questions.
    Decoteau Wilkerson
    Content Marketing Specialist
    Jama Software
    Oregon
  • Gulam Emadi
    Gulam Emadi Member Posts: 13
    edited March 2022
    For the record, we ran into the exact same scenario today. We have a released test plan, but have been making updates in the meantime. We want to execute on the released plan, but cannot create our test cycle from the baseline for the release.
  • Manel Moreno
    Manel Moreno Member Posts: 11
    edited March 2023

    We have Exactly the same need: we need to execute the Test Cases as they were on the release date (baselined).

    Is the only solution to clone (re-use) them? How to solve then the problem with the traceability to the released requirements (also in the same baseline)?

    ------------------------------
    Manel Moreno
    SW Test Manager
    Systelab Technologies
    ------------------------------
    -------------------------------------------
    Original Message:
    Sent: 03-28-2022 09:23
    From: Gulam Emadi
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    For the record, we ran into the exact same scenario today. We have a released test plan, but have been making updates in the meantime. We want to execute on the released plan, but cannot create our test cycle from the baseline for the release.

    ------------------------------
    Gulam Emadi
    ------------------------------

    Original Message:
    Sent: 04-16-2021 16:04
    From: Decoteau Wilkerson
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    Hi Bartek, 

    Thanks for reaching out! There is no way to create a Test Plan/Cycle on a Baseline. 

    You could visit our Ideation module and submit this as an idea. This is a valuable space where we solicit and gather product feedback. You can go here, and use the search functionality to see if your idea is already in there. If it is, then you can vote and comment on the card. If there isn't, please post a new idea card. 

    Let us know if you have any questions.

    ------------------------------
    Decoteau Wilkerson
    Jama Software
    OR

    Original Message:
    Sent: 04-14-2021 23:49
    From: Bartek LastName
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    Hi,

    Sometime ago I created baseline for my test cases in JAMA. After the baseline was created, we started updating the test cases for new version of the product. However, I still have to execute tests from baseline for previous version of the product. Is it any solution to create test plan based on the baseline which i created ( in the test plan/test cycle I would like to have test run corresponding with version of the test cases from baseline).

    Any GUI option or REST API to support creating test run based on the specific version of the test case?

    Thanks in advance
    Bartek

    ------------------------------
    Bartek LastName
    S3 Group
    ------------------------------
  • [Deleted User]
    [Deleted User] Posts: 152
    edited March 2023

    Hi Manel,

    The workaround would be to re-use them, but there isn't currently a way to resolve the traceability bit. That said, I'd recommend voting on the idea card Gulam submitted (if you haven't already), as well as sharing your usage case and how traceability comes into play, to add additional context for our Product team. 

    ------------------------------
    Carly Rossi // she/her
    Community Manager // Jama Software
    Portland, OR
    ------------------------------
    -------------------------------------------
    Original Message:
    Sent: 03-14-2023 05:12
    From: Manel Moreno
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    We have Exactly the same need: we need to execute the Test Cases as they were on the release date (baselined).

    Is the only solution to clone (re-use) them? How to solve then the problem with the traceability to the released requirements (also in the same baseline)?

    ------------------------------
    Manel Moreno
    SW Test Manager
    Systelab Technologies
    ------------------------------

    Original Message:
    Sent: 03-28-2022 09:23
    From: Gulam Emadi
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    For the record, we ran into the exact same scenario today. We have a released test plan, but have been making updates in the meantime. We want to execute on the released plan, but cannot create our test cycle from the baseline for the release.

    ------------------------------
    Gulam Emadi

    Original Message:
    Sent: 04-16-2021 16:04
    From: Decoteau Wilkerson
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    Hi Bartek, 

    Thanks for reaching out! There is no way to create a Test Plan/Cycle on a Baseline. 

    You could visit our Ideation module and submit this as an idea. This is a valuable space where we solicit and gather product feedback. You can go here, and use the search functionality to see if your idea is already in there. If it is, then you can vote and comment on the card. If there isn't, please post a new idea card. 

    Let us know if you have any questions.

    ------------------------------
    Decoteau Wilkerson
    Jama Software
    OR

    Original Message:
    Sent: 04-14-2021 23:49
    From: Bartek LastName
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    Hi,

    Sometime ago I created baseline for my test cases in JAMA. After the baseline was created, we started updating the test cases for new version of the product. However, I still have to execute tests from baseline for previous version of the product. Is it any solution to create test plan based on the baseline which i created ( in the test plan/test cycle I would like to have test run corresponding with version of the test cases from baseline).

    Any GUI option or REST API to support creating test run based on the specific version of the test case?

    Thanks in advance
    Bartek

    ------------------------------
    Bartek LastName
    S3 Group
    ------------------------------
  • Manel Moreno
    Manel Moreno Member Posts: 11
    edited March 2023

    Hi Carly,

    I added there a couple of impacts we are facing if we re-use the Test Cases. I Hope this could be solved in a different way in the future.

    ------------------------------
    Manel Moreno
    SW Test Manager
    Systelab Technologies
    ------------------------------
    -------------------------------------------
    Original Message:
    Sent: 03-28-2023 14:55
    From: Carly Rossi
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    Hi Manel,

    The workaround would be to re-use them, but there isn't currently a way to resolve the traceability bit. That said, I'd recommend voting on the idea card Gulam submitted (if you haven't already), as well as sharing your usage case and how traceability comes into play, to add additional context for our Product team. 

    ------------------------------
    Carly Rossi // she/her
    Community Manager // Jama Software
    Portland, OR
    ------------------------------

    Original Message:
    Sent: 03-14-2023 05:12
    From: Manel Moreno
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    We have Exactly the same need: we need to execute the Test Cases as they were on the release date (baselined).

    Is the only solution to clone (re-use) them? How to solve then the problem with the traceability to the released requirements (also in the same baseline)?

    ------------------------------
    Manel Moreno
    SW Test Manager
    Systelab Technologies

    Original Message:
    Sent: 03-28-2022 09:23
    From: Gulam Emadi
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    For the record, we ran into the exact same scenario today. We have a released test plan, but have been making updates in the meantime. We want to execute on the released plan, but cannot create our test cycle from the baseline for the release.

    ------------------------------
    Gulam Emadi

    Original Message:
    Sent: 04-16-2021 16:04
    From: Decoteau Wilkerson
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    Hi Bartek, 

    Thanks for reaching out! There is no way to create a Test Plan/Cycle on a Baseline. 

    You could visit our Ideation module and submit this as an idea. This is a valuable space where we solicit and gather product feedback. You can go here, and use the search functionality to see if your idea is already in there. If it is, then you can vote and comment on the card. If there isn't, please post a new idea card. 

    Let us know if you have any questions.

    ------------------------------
    Decoteau Wilkerson
    Jama Software
    OR

    Original Message:
    Sent: 04-14-2021 23:49
    From: Bartek LastName
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    Hi,

    Sometime ago I created baseline for my test cases in JAMA. After the baseline was created, we started updating the test cases for new version of the product. However, I still have to execute tests from baseline for previous version of the product. Is it any solution to create test plan based on the baseline which i created ( in the test plan/test cycle I would like to have test run corresponding with version of the test cases from baseline).

    Any GUI option or REST API to support creating test run based on the specific version of the test case?

    Thanks in advance
    Bartek

    ------------------------------
    Bartek LastName
    S3 Group
    ------------------------------
  • [Deleted User]
    [Deleted User] Posts: 152
    edited March 2023

    Thanks Manel! Definitely keep an eye on that idea card for updates; I'll be closing this thread due to its age.

    ------------------------------
    Carly Rossi // she/her
    Community Manager // Jama Software
    Portland, OR
    ------------------------------
    -------------------------------------------
    Original Message:
    Sent: 03-30-2023 01:07
    From: Manel Moreno
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    Hi Carly,

    I added there a couple of impacts we are facing if we re-use the Test Cases. I Hope this could be solved in a different way in the future.

    ------------------------------
    Manel Moreno
    SW Test Manager
    Systelab Technologies
    ------------------------------

    Original Message:
    Sent: 03-28-2023 14:55
    From: Carly Rossi
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    Hi Manel,

    The workaround would be to re-use them, but there isn't currently a way to resolve the traceability bit. That said, I'd recommend voting on the idea card Gulam submitted (if you haven't already), as well as sharing your usage case and how traceability comes into play, to add additional context for our Product team. 

    ------------------------------
    Carly Rossi // she/her
    Community Manager // Jama Software
    Portland, OR

    Original Message:
    Sent: 03-14-2023 05:12
    From: Manel Moreno
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    We have Exactly the same need: we need to execute the Test Cases as they were on the release date (baselined).

    Is the only solution to clone (re-use) them? How to solve then the problem with the traceability to the released requirements (also in the same baseline)?

    ------------------------------
    Manel Moreno
    SW Test Manager
    Systelab Technologies

    Original Message:
    Sent: 03-28-2022 09:23
    From: Gulam Emadi
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    For the record, we ran into the exact same scenario today. We have a released test plan, but have been making updates in the meantime. We want to execute on the released plan, but cannot create our test cycle from the baseline for the release.

    ------------------------------
    Gulam Emadi

    Original Message:
    Sent: 04-16-2021 16:04
    From: Decoteau Wilkerson
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    Hi Bartek, 

    Thanks for reaching out! There is no way to create a Test Plan/Cycle on a Baseline. 

    You could visit our Ideation module and submit this as an idea. This is a valuable space where we solicit and gather product feedback. You can go here, and use the search functionality to see if your idea is already in there. If it is, then you can vote and comment on the card. If there isn't, please post a new idea card. 

    Let us know if you have any questions.

    ------------------------------
    Decoteau Wilkerson
    Jama Software
    OR

    Original Message:
    Sent: 04-14-2021 23:49
    From: Bartek LastName
    Subject: Create Test Plan/ Test Runs from JAMA test case baseline

    Hi,

    Sometime ago I created baseline for my test cases in JAMA. After the baseline was created, we started updating the test cases for new version of the product. However, I still have to execute tests from baseline for previous version of the product. Is it any solution to create test plan based on the baseline which i created ( in the test plan/test cycle I would like to have test run corresponding with version of the test cases from baseline).

    Any GUI option or REST API to support creating test run based on the specific version of the test case?

    Thanks in advance
    Bartek

    ------------------------------
    Bartek LastName
    S3 Group
    ------------------------------
This discussion has been closed.