Baselines
is it possible to restore to a baseline?
------------------------------Joseph Sitomer
Think Surgical
Fremont CA
------------------------------
Comments
-
Yes, it is possible.
Refer to this link: https://help.jamasoftware.com/ah/en/manage-content/baselines/replace-current-items-with-a-baselined-version.html
------------------------------
Anthony C.
------------------------------
-------------------------------------------
Original Message:
Sent: 07-25-2023 13:20
From: Joseph Sitomer
Subject: Baselinesis it possible to restore to a baseline?
------------------------------
Joseph Sitomer
Think Surgical
Fremont CA
------------------------------
0 -
A piggy-back question. As I understand it, Jama allows a project-wide Replace with baseline. Is there a converse project-wide of Replace with current? The online help references the term "Replace with current", but I have not found such a project-wide feature. So far I am only aware of doing this at the individual item level using Make Current feature.
------------------------------
Additionally is there a mechanism to selectively pick which items to restore to a baseline, when the project-wide Replace with current operation is performed?
Kenneth Sinsuan
TrelllisWare
San Diego CA
------------------------------
-------------------------------------------
Original Message:
Sent: 07-25-2023 14:16
From: Anthony C
Subject: BaselinesYes, it is possible.
Refer to this link: https://help.jamasoftware.com/ah/en/manage-content/baselines/replace-current-items-with-a-baselined-version.html
------------------------------
Anthony C.
------------------------------
Original Message:
Sent: 07-25-2023 13:20
From: Joseph Sitomer
Subject: Baselinesis it possible to restore to a baseline?
------------------------------
Joseph Sitomer
Think Surgical
Fremont CA
------------------------------
0 -
I've never seen a project-wide option like that and I wouldn't think there is. The versions of the items you see in each project are the "current" version. I've never done a "replace with baseline" but if it works the same as "make current" for individual items, it's going to create a new version of the item(s) with the content from the baseline. That new version becomes the current version for each item. The version that had been current prior to the replace then becomes a previous version.
------------------------------
Alex
Fujifilm Sonosite
------------------------------
-------------------------------------------
Original Message:
Sent: 08-23-2023 12:11
From: Kenneth Sinsuan
Subject: BaselinesA piggy-back question. As I understand it, Jama allows a project-wide Replace with baseline. Is there a converse project-wide of Replace with current? The online help references the term "Replace with current", but I have not found such a project-wide feature. So far I am only aware of doing this at the individual item level using Make Current feature.
------------------------------
Additionally is there a mechanism to selectively pick which items to restore to a baseline, when the project-wide Replace with current operation is performed?
Kenneth Sinsuan
TrelllisWare
San Diego CA
------------------------------
Original Message:
Sent: 07-25-2023 14:16
From: Anthony C
Subject: BaselinesYes, it is possible.
Refer to this link: https://help.jamasoftware.com/ah/en/manage-content/baselines/replace-current-items-with-a-baselined-version.html
------------------------------
Anthony C.
Original Message:
Sent: 07-25-2023 13:20
From: Joseph Sitomer
Subject: Baselinesis it possible to restore to a baseline?
------------------------------
Joseph Sitomer
Think Surgical
Fremont CA
------------------------------
Alex
Fujifilm Sonosite0